Finish
/clear
/batch
/title,Theprocess of creating a tower of concrete cable-stayed bridge modeling
/filename,atower of concrete cable-stayed bridge
/batch
/input,menust,tmp
*set,L1,98,19
*set,L2,2.54
*set,L3,42
*set,L4,4.04
*set,L5,48.16
*set,L6,1.42
*set,L7,5.16
*set,L8,18.18
*set,L9,20.48
*set,a,80°
*set,Q,5
*set,C,3
*set,M,7
/prep7
*dim,towd,96.8,11
et,1,solid65
mp,ex,1,6.84e10
mp,prxy,1,0.2
r,1,0,1e3
DIST,L1,98.19
DIST,L2,2.54
DIST,L3,42
DIST,L4,4.04
DIST,L5,48.16
DIST,L6,1.42
DIST,L7,5.16
DIST,L8,18.18
DIST,L9,20.48
Angle,a,80°
K,1,0,0,0
K,2,3.25,0,0
K,3,34.79,0,0
K,4,38.04,0,0
K,5,10.28,0,41.4
K,6,27.76,0,41.4
K,7,27.08,0,45.4
K,8,10.96,0,45.4
K,9,19.02,0,93.13
K,10,21.6,0,96.8
K,11,16.44,0,96.8
LSTR,1,2
LSTR,2,5
LSTR,5,6
LSTR,6,3
LSTR,3,4
LSTR,4,10
LSTR,10,11
LSTR,11,7
LSTR,7,8
LSTR,8,9
LSTR,9,7
AL,1,2,3,4,5,6,10,11
AL,7,8,9
ASBA,1,2
K,12,0,10,0
LSTR,1,12
VDRAG,ALL,,,,,,12
ESIZE,1,0
AMESH,1